Use of ECORASTER as a separating layer for a lunging ring.

  • Year of implementation: 2015
  • Nature of surface: old sand surface without proper substrate
  • Area: 240 m²
  • Construction time: 2 days

This project consisted of the renovation of a 240 m² lunging ring. One of the main issues with the site was the total lack of stabilization and the uneven sand layer. The result: Regular lunging resulted in deep hoof marks and a hardening of the ground in the entire area.

As a first step, the old soil layer was removed from the circle area and the ground was leveled. After that, ECORASTER TE30 was installed on the surface and recovered with non-slip, shear-resistant equestrian sand.